Activities at the Port Slavonski Brod in the period from 01.06. until 01.07.2019. :
Although throughout June the weather was relatively bad with frequent rains and high water levels the works continue on Mon. 06/17/2019. when the water level has dropped to an acceptable level.
The contractor started with all the necessary actions to repair the work platform for digging the diaphragm that was underwater for a month due to the high water level: rehabilitation of access roads, water pumping, sludge cleaning, transportation of equipment (which was transferred to a safe place) and continue work on excavation of diaphragm "dilation / field No. III"