Preliminary work during September consisted of site maintenance work for the functioning of roads and smooth performance of the work. Within the preparatory work they were security works and works for maintenance of site roads.
On the construction of berths No.4 and 5, the works on the construction of the plateau continued as well as the works on the installation of the diaphragm and the pilaster. The works of technical observation (inclination installations) were carried out and the reinforced concrete works on the construction of longitudinal and transverse beams of the lower grill IV began.
At the site of construction of the industrial port track and the industrial port road with infrastructure started with excavation works, procurement and installation of stormwater drainage pipes were carried out.
Works on the hydrant network included preparatory works, embankment works in the facility below the base plate of the basin and reinforced concrete works on base plate of the retention basin.