After high water leves of River Sava in December 2019, in January water levels droped and contractor started with works. Works consisted of cleaning the silt and rehabilitating of the access roads.
The construction of PI panels is continuing and reinforcement works are also being carried out for the AB transverse and longitudinal walls of vertical quays no. 4 and 5.
Some railway turns are being brought to the construction site for the continuation of the railway through out the Port of Slavonski Brod.
The retention pool with a pumping station was completed and 610 m of hidden grid was built.