Continuation of reinforcement, carpentry and concrete works on the production of transverse and longitudinal beams of the upper grill of the berth 4 and 5 construction and the final slab of the berth construction 4 and 5, complete with precipitation drainage.
Excavation with laying of geotextiles and underlying concrete, preparation of reinforcement, formwork and execution of anchor walls of dilatation 1, 2, 3 and 4. By the end of July, all anchor walls of the previously mentioned dilatations were performed.
Construction of track facilities and preparation of embankments between the anchor wall and the pier construction.
Works on the preparation and arrangement of manipulative surfaces - lower structure, installation of geotextiles and geogrides as well as filling with stone material of geogrides with precipitation drainage and laying of a new track type 49E1 and switches. The work includes the installation of rails and switches on concrete blocks with rough regulation in direction and height.