Current state of works – February 2020

Current state of works – February 2020

After cleaning the sludge on site and the rehabilitation of access roads in January 2020, caused by the high water levels in December 2019, we started with the continued construction of the PI panel and  also performed reinforcement work for AB transverse and longitudinal walls of vertical coast no.4 and 5.

Due to favourable weather conditions, the building of drainage and gullies on the project area connection 4 and 5.

 

Kontakt info

Šetalište braće Radić 19a, HR-35000 Slavonski Brod
Telefon: +385 (0)35 404 430, Telefaks: +385 (0)35 250 538
E-mail: info@lusb.hr

OIB

OIB: 14562482156

Copyright © 2017 All Rights Reserved.