Current state of works – March 2020

Current state of works – March 2020

The construction of the port infrastructure in March included the following works:

  • Fabrication of reinforcement, formwork of the upper structure coastal structures. Transverse walls and longitudinal walls in axis A and axis C are completed.
  • Continued production of prefabricated PI panels that are supported by longitudinal beam, 10 cm thick and 2.2m in reinforced concrete with compressive strength C30 / 37 (XC / XF1, VDP1).
  • Construction of hydrant network, drainage and test field of the industrial port road structure