On 24.02.2021, in compliance with all recommended epidemiological recommendations of the Institute of Public Health, a second press conference of the EU Project "Slavonski Brod port infrastructure construction and upgrade"was held at the Port Authority of Slavonski Brod..
The topic of the press conference was "Explanation of the process of execution of works on the Port of Slavonski Brod" and the goal was to bring closer the process of realization of works on the Project.
The works were presented by Mr. Tomaž Tušar, and Mr. Goran Batušić representatives of the main contractor GH Holding d.o.o. from Ljubljana.
The project was presented through 4 phases of implementation:
- execution of archeological research works (in the entire project area),
- geodetic survey, and staking out of the entire area,
- earthworks (excavation and removal of materials)
- realization of the project through 6 building permits:
- construction of new berths no. 4 and no. 5
- Industrial track and industrial road with infrastructure
- Hydrant network
- Power line with outdoor lighting
- Auxiliary facilities of the container terminal
- Outdoor fence